Skip to main content
← Back

Park Titan Phase IV, Marunji

by Pride Purple Infrastructure. Marunji, Pune 411057. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
1 year 5 months awayPossession date unchanged since launch
Concrete structure (RCC)
8%Mid-constructionAverage across 2 buildings
Units booked
120 of 23950% booked
Price per sq ft (incl. balconies and terrace)
₹10,7002026 so far · 21 salesdown 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK113
3 BHK126
Total units239
Buildings2
Land1.8 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
990 sq ft₹1.00 – 1.04 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,300 per sq ft17 sales
2025up 5% on 2024₹10,800 per sq ft16 sales
2026 so fardown 1% on 2025₹10,700 per sq ft21 sales

Compared with 6 similar projects in PIN 411057

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)March 2028December 2028
Concrete structure (RCC) complete8%72%
Share of units booked50%66%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 6 months of the promised 3 years 11 months have passed
Concrete structure (RCC) 8% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 8%Jun 2025: Concrete structure (RCC) 8%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 8%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 8%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%0%120
100%0%0%59

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Park Titan Phase IV (MahaRERA P52100055911) is a residential project by Pride Purple Infrastructure in Marunji, Pune 411057. It was launched in April 2024. It has 239 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 8% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

120 of its 239 units are booked (50%). 80% of the 2026 (so far) sales we found here were at ₹10,700 per sq ft or less (down 1% on 2025), counting balconies and terrace in the size, based on 21 registered sales. Most buyers paid ₹1.00–1.04 crore for flats of 990 sq ft.

Pride's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA27
Completed without extending the possession date8
Completed after an extension, or lapsed8
Under construction11
Possession date extended by the builder0
Typical time from launch to 100% structure2 years 7 months
Complaints on MahaRERA, all Pride projects12 (11 of 27 projects)

See all Pride projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055911.Check it on MahaRERA (P52100055911)All projects in Wakad, Hinjewadi, Marunji