Park Titan Phase III, Marunji
by Pride Purple Infrastructure. Marunji, Pune 411057. View on Google Maps
- Launched
- 4 years 4 months promised
- Possession date (MahaRERA)
- 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 69%Mid-constructionAverage across 3 buildings
- Units booked
- 359 of 41187% booked
- Price per sq ft (incl. balconies and terrace)
- ₹10,9002025 · 11 salesup 7% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 136 |
|---|---|
| 3 BHK | 275 |
| Total units | 411 |
| Buildings | 3 |
| Land | 1.8 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 980 – 1,000 sq ft | ₹1.04 – 1.09 crore |
Based on flats sold in 2025.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹10,200 per sq ft | 11 sales |
|---|---|---|
| 2025up 7% on 2024 | ₹10,900 per sq ft | 11 sales |
Compared with 6 similar projects in PIN 411057
Projects with 200–900 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 4 mths | 4 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | June 2027 | March 2027 |
| Concrete structure (RCC) complete | 69% | 92% |
| Share of units booked | 87% | 86% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sensorium, Phase VII | February 2023 | December 2026 | 100% | 238 of 258 booked (92%) |
| 57 Elevate | February 2023 | December 2026 | 83% | 198 of 244 booked (81%) |
| Hinjewadi Project | March 2023 | June 2027 | 100% | 375 of 430 booked (87%) |
| Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops | April 2023 | March 2028 | 75% | 518 of 603 booked (86%) |
| Life Republic Sector R13/13th Avenue/Aros/Phase I | December 2022 | December 2026 | 100% | 689 of 739 booked (93%) |
| ANP Ultimus | November 2022 | June 2027 | 83% | 645 of 840 booked (77%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 69% | 2% | 359 | |
| 100% | 0% | 0% | 346 | |
| 100% | 0% | 0% | 206 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Park Titan Phase III (MahaRERA P52100049631) is a residential project by Pride Purple Infrastructure in Marunji, Pune 411057. It was launched in February 2023. It has 411 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 69% complete, final finishes 2% complete. MahaRERA records do not show it as ready to move in.
359 of its 411 units are booked (87%). 80% of the 2025 sales we found here were at ₹10,900 per sq ft or less (up 7% on 2024), counting balconies and terrace in the size, based on 11 registered sales. Most buyers paid ₹1.04–1.09 crore for flats of 980–1,000 sq ft.
Pride's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 27 |
|---|---|
| Completed without extending the possession date | 8 |
| Completed after an extension, or lapsed | 8 |
| Under construction | 11 |
| Possession date extended by the builder | 0 |
| Typical time from launch to 100% structure | 2 years 7 months |
| Complaints on MahaRERA, all Pride projects | 12 (11 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.