Skip to main content
← Back

Urban Life Phase 1, Talegaon Dabhade

by Kakade Vtp Associates. Talegaon Dabhade, Pune 410506. View on Google Maps

Launched
4 years 5 months originally promised
Possession date (MahaRERA)
3 years 10 months ago. No further extension recordedExtended by 1 year (originally December 2021). Why possession dates change
Concrete structure (RCC)
75%Mid-constructionAverage across 4 buildings
Units booked
208 of 34361% booked

Project facts

1 RK2
1 BHK144
2 BHK197
Total units343
Buildings4
Land2.8 acres
Complaints on MahaRERA (filed by or against the builder)15

Since Dec 2025: structure 100% → 75% · final finishes 70% → 75% · complaints 14 → 15

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 5 months have passed
Concrete structure (RCC) 75% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 75%Dec 2023: Concrete structure (RCC) 65%Jun 2024: Concrete structure (RCC) 75%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 75%Dec 2023: Final finishes 50%Jun 2024: Final finishes 50%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 70%Jul 2026: Final finishes 75%Excavation 75%Concrete structure (RCC) 75%Final finishes 75%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%75%75%208
100%100%70%208
100%100%50%170
100%75%50%155
100%65%50%212

"—" means MahaRERA shows no figure for that update.

About this project

Urban Life Phase 1 (MahaRERA P52100001269) is a residential project by Kakade Vtp Associates in Talegaon Dabhade, Pune 410506. It was launched in July 2017. It has 343 units in 4 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2022, after an extension of 1 year from the original December 2021. That date has passed and no further extension has been recorded. Construction, averaged across its 4 buildings: excavation 75% complete, structure (RCC) 75% complete, final finishes 75% complete. MahaRERA records do not show it as ready to move in.

208 of its 343 units are booked (61%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 100% to 75%.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100001269.Check it on MahaRERA (P52100001269)All projects in Talegaon Dabhade, Darumbare