Somani Towers, Punawale
by Somani Realty AOP. Punawale, Pune 411033. View on Google Maps
- Launched
- 3 years 5 months originally promised
- Possession date (MahaRERA)
- 10 months ago. No further extension recordedExtended by 5 years (originally December 2020). Why possession dates change
- Concrete structure (RCC)
- 40%Mid-constructionAverage across 5 buildings
- Units booked
- 204 of 30068% booked
- Price per sq ft (incl. balconies and terrace)
- ₹7,8002026 so far · 14 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 64 |
|---|---|
| 2 BHK | 235 |
| 3 BHK | 1 |
| Total units | 300 |
| Buildings | 5 |
| Land | 2.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 15 |
Since Dec 2025: complaints 2 → 15
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 660 – 690 sq ft | ₹51 – 54 lakh |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹7,800 per sq ft | 30 sales |
|---|---|---|
| 2026 so farabout the same as 2025 | ₹7,800 per sq ft | 14 sales |
Rate vs other Punawale projects, 2026: about 15% lower
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 40% | 40% | 12% | 204 | |
| 40% | 38% | 8% | — | |
| 40% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Somani Towers (MahaRERA P52100001830) is a residential project by Somani Realty AOP in Punawale, Pune 411033. It was launched in July 2017. It has 300 units in 5 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2025, after an extension of 5 years from the original December 2020. That date has passed and no further extension has been recorded. Construction, averaged across its 5 buildings: excavation 40% complete, structure (RCC) 40% complete, final finishes 12% complete. MahaRERA records do not show it as ready to move in.
204 of its 300 units are booked (68%). 80% of the 2026 (so far) sales we found here were at ₹7,800 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 14 registered sales. Buyers here paid a rate about 15% lower than at other Punawale projects in 2026. Most buyers paid ₹51–54 lakh for flats of 660–690 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.