Royal Oak, Wakad

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Lifestyle Developments. Wakad, Pune 411057. View on Google Maps

Launched
8 years 5 months promised
Possession date (MahaRERA)
10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Finishing stageAverage across 4 buildings
Units booked
295 of 32192% booked
Price per sq ft (incl. balconies and terrace)
₹8,8002024 · 53 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK6
1 BHK99
2 BHK208
3 BHK2
Other units (shops, offices or not given by type)6
Total units321
Buildings4
Land2.1 acres
Landowner share16
Reserved units4
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 28% → 100% · final finishes 20% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
720 – 780 sq ft₹62 – 67 lakh

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,800 per sq ft53 sales

Rate vs other Wakad projects, 2024: similar

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 8 years 5 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 65%Jun 2024: Excavation 65%Dec 2024: Excavation 65%Jun 2025: Excavation 65%Dec 2025: Excavation 65%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 28%Jun 2024: Concrete structure (RCC) 28%Dec 2024: Concrete structure (RCC) 28%Jun 2025: Concrete structure (RCC) 28%Dec 2025: Concrete structure (RCC) 28%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 20%Jun 2024: Final finishes 20%Dec 2024: Final finishes 20%Jun 2025: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%295
65%28%20%295
65%28%20%200

"—" means MahaRERA shows no figure for that update.

About this project

Royal Oak (MahaRERA P52100001837) is a residential project by Lifestyle Developments in Wakad, Pune 411057. It was launched in July 2017. It has 321 units in 4 buildings: 315 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

295 of its 321 units are booked (92%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 28% to 100%. 80% of the 2024 sales we found here were at ₹8,800 per sq ft or less, counting balconies and terrace in the size, based on 53 registered sales. Buyers here paid a rate similar to other Wakad projects in 2024. Most buyers paid ₹62–67 lakh for flats of 720–780 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.