Purva Silversands Phase 2, Mundhwa

by Pune Projects LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
5 years 3 months originally promised
Possession date (MahaRERA)
2 years 11 months ago. No further extension recordedExtended by 1 year (originally November 2022). Why possession dates change
Concrete structure (RCC)
100%Nearing possession
Units booked
211 of 33663% booked
Price per sq ft (incl. balconies and terrace)
₹13,100studios · 2026 so far · 44 salesup 7% on 202580% of the 2026 studio sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK82
Other units (shops, offices or not given by type)254
Total units336
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)22
Share on WhatsApp

What buyers paid here

Studios (under 450 sq ft)

₹13,100 per sq ft · studios · 2026 so far · 44 sales

80% of the 2026 studio sales we found were at this rate or less

2025₹12,300 per sq ft72 sales
2026 so farup 7% on 2025₹13,100 per sq ft44 sales

Sizes 280 – 320 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 3 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 4%Dec 2024: Final finishes 4%Jun 2025: Final finishes 4%Dec 2025: Final finishes 41%Excavation 100%Concrete structure (RCC) 100%Final finishes 41%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%41%211
100%100%4%122
100%100%0%138

"—" means MahaRERA shows no figure for that update.

About this project

Purva Silversands Phase 2 (MahaRERA P52100005377) is a residential project by Pune Projects LLP in Mundhwa, Pune 411036. It was launched in August 2017. It has 336 units in 1 building: 82 homes (1 RK) and 254 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in November 2023, after an extension of 1 year from the original November 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 41% complete. MahaRERA records do not show it as ready to move in.

211 of its 336 units are booked (63%). Its studios (under 450 sq ft) sold at ₹13,100 per sq ft or less in 2026 (44 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100005377.Check it on MahaRERA (P52100005377)All projects in Mundhwa, Keshavnagar