Skip to main content
← Back

Platinum Park Phase II, Undri

by Ranjeet Property Developers India Pvt. Ltd.. Undri, Pune 411060. View on Google Maps

Launched
5 years 4 months originally promised
Possession date (MahaRERA)
2 months awayExtended by 4 years (originally December 2022). Why possession dates change
Concrete structure (RCC)
10%Mid-constructionAverage across 2 buildings
Units booked
9 of 8810% booked

Project facts

2 BHK81
3 BHK7
Total units88
Buildings2
Land2.4 acres
Complaints on MahaRERA (filed by or against the builder)10

Since Dec 2025: complaints 1 → 10

Share on WhatsApp

Compared with 5 similar projects in PIN 411060

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411060
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 4 mths5 yrs 10 mths
Possession date extendedBy 4 years5 of 5
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete10%100%
Share of units booked10%57%
Complaints on MahaRERA (filed by or against the builder)102

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 4 months have passed
Concrete structure (RCC) 10% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 10%Jun 2024: Concrete structure (RCC) 10%Dec 2024: Concrete structure (RCC) 10%Jun 2025: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 10%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 10%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%9

"—" means MahaRERA shows no figure for that update.

About this project

Platinum Park Phase II (MahaRERA P52100007013) is a residential project by Ranjeet Property Developers India Pvt. Ltd. in Undri, Pune 411060. It was launched in August 2017. It has 88 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 4 years from the original December 2022. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 10% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

9 of its 88 units are booked (10%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100007013.Check it on MahaRERA (P52100007013)All projects in Mohammadwadi, Undri