Shuban Enclave, Ravet
by Sahyadri Devcon. Ravet, Pune 412101. View on Google Maps
- Launched
- 3 years 4 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 6 years (originally December 2020). Why possession dates change
- Concrete structure (RCC)
- 67%Mid-constructionAverage across 3 buildings
- Units booked
- 4 of 567% booked
- Price per sq ft (incl. balconies and terrace)
- ₹7,1002026 so far · 16 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 56 |
|---|---|
| Total units | 56 |
| Buildings | 3 |
| Land | 0.9 acres |
| Landowner share | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 2 → 4 · structure 53% → 67%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 850 sq ft | ₹60 – 65 lakh |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2026 so far | ₹7,100 per sq ft | 16 sales |
|---|
Rate vs other Ravet projects, 2026: about 20% lower
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 67% | 0% | 4 | |
| 67% | 53% | 0% | 2 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Shuban Enclave (MahaRERA P52100007474) is a residential project by Sahyadri Devcon in Ravet, Pune 412101. It was launched in August 2017. It has 56 units in 3 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 6 years from the original December 2020. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 67% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
4 of its 56 units are booked (7%). Since the December 2025 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 53% to 67%. 80% of the 2026 (so far) sales we found here were at ₹7,100 per sq ft or less, counting balconies and terrace in the size, based on 16 registered sales. Buyers here paid a rate about 20% lower than at other Ravet projects in 2026. Most buyers paid ₹60–65 lakh for flats of 850 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.