Dnyanada City and Dnyanada Commercial Center, Chakan
by Bhagwan Narayan Pokharkar. Chakan, Pune 410501. View on Google Maps
- Launched
- 6 years 4 months originally promised
- Possession date (MahaRERA)
- 1 year 2 months awayExtended by 4 years (originally December 2023). Why possession dates change
- Concrete structure (RCC)
- 98%Mid-constructionAverage across 5 buildings
- Units booked
- 336 of 52664% booked
Project facts
| 1 RK | 3 |
|---|---|
| 1 BHK | 161 |
| 2 BHK | 131 |
| 3 BHK | 9 |
| Other units (shops, offices or not given by type) | 222 |
| Total units | 526 |
| Buildings | 5 |
| Land | 6.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 5 similar projects in PIN 410501
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 6 yrs 4 mths | 4 yrs 10 mths |
| Possession date extended | By 4 years | 5 of 5 |
| Possession date (MahaRERA) | December 2027 | December 2030 |
| Concrete structure (RCC) complete | 98% | 92% |
| Share of units booked | 64% | 83% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 6 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aapla Ghar Moshi Annex Phase I | August 2017 | December 2024 | 98% | 259 of 296 booked (88%) |
| Phase I - Buildings A, A1, P and S,T,U Combined wing | August 2017 | December 2030 | 100% | 113 of 245 booked (46%) |
| Aapla Ghar Chakan Talegaon Phase I | September 2017 | December 2024 | 44% | 259 of 272 booked (95%) |
| Dwarka PROJECT2 | July 2017 | December 2020 | 92% | 159 of 192 booked (83%) |
| Playtor Chakan Midc-Phase 1 | February 2018 | December 2023 | 50% | 62 of 262 booked (24%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 65% | 336 | |
| 100% | 88% | 57% | 336 | |
| 50% | 50% | 38% | 251 |
"—" means MahaRERA shows no figure for that update.
About this project
Dnyanada City and Dnyanada Commercial Center (MahaRERA P52100009874) is a residential project by Bhagwan Narayan Pokharkar in Chakan, Pune 410501. It was launched in August 2017. It has 526 units in 5 buildings: 304 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 222 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) 98% complete, final finishes 65% complete. MahaRERA records do not show it as ready to move in.
336 of its 526 units are booked (64%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.