Aapla Ghar Chakan Talegaon Phase I, Bhamboli
by Maple Shelters Chakan 1. Bhamboli, Pune 410501. View on Google Maps
- Launched
- 6 years 3 months originally promised
- Possession date (MahaRERA)
- 1 year 10 months ago. No further extension recordedExtended by 1 year (originally December 2023). Why possession dates change
- Concrete structure (RCC)
- 44%Mid-constructionAverage across 8 buildings
- Units booked
- 259 of 27295% booked
Project facts
| 1 RK | 16 |
|---|---|
| 1 BHK | 144 |
| 2 BHK | 112 |
| Total units | 272 |
| Buildings | 8 |
| Land | 4.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 14 |
Since Dec 2025: booked 254 → 259
Compared with 5 similar projects in PIN 410501
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 6 yrs 3 mths | 4 yrs 10 mths |
| Possession date extended | By 1 year | 5 of 5 |
| Possession date passed | Yes, due December 2024 | 1 ready to move; 3 also past their date |
| Concrete structure (RCC) complete | 44% | 98% |
| Share of units booked | 95% | 64% |
| Complaints on MahaRERA (filed by or against the builder) | 14 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Phase I - Buildings A, A1, P and S,T,U Combined wing | August 2017 | December 2030 | 100% | 113 of 245 booked (46%) |
| Aapla Ghar Moshi Annex Phase I | August 2017 | December 2024 | 98% | 259 of 296 booked (88%) |
| Dnyanada City and Dnyanada Commercial Center | August 2017 | December 2027 | 98% | 336 of 526 booked (64%) |
| Dwarka PROJECT2 | July 2017 | December 2020 | 92% | 159 of 192 booked (83%) |
| Playtor Chakan Midc-Phase 1 | February 2018 | December 2023 | 50% | 62 of 262 booked (24%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 44% | 43% | 259 | |
| 50% | 44% | 43% | 254 | |
| 50% | 44% | 41% | 259 | |
| 88% | 48% | 36% | 243 |
"—" means MahaRERA shows no figure for that update.
About this project
Aapla Ghar Chakan Talegaon Phase I (MahaRERA P52100012098) is a residential project by Maple Shelters Chakan 1 in Bhamboli, Pune 410501. It was launched in September 2017. It has 272 units in 8 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction, averaged across its 8 buildings: excavation 50% complete, structure (RCC) 44% complete, final finishes 43% complete. MahaRERA records do not show it as ready to move in.
259 of its 272 units are booked (95%). Since the December 2025 update, 5 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.