Avalon City - C2, Dapodi
by Classic Promoters and Builders Private Limited. Dapodi, Pune 411012. View on Google Maps
- Launched
- 3 years 10 months originally promised
- Possession date (MahaRERA)
- 2 years 1 month ago. No further extension recordedExtended by 3 years (originally September 2021). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 81 of 8892% booked
Project facts
| 1 BHK | 15 |
|---|---|
| 2 BHK | 73 |
| Total units | 88 |
| Buildings | 2 |
| Land | 1.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 79 → 81
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 81 | |
| 100% | 100% | 0% | 79 | |
| 100% | 89% | 0% | 59 | |
| 100% | 89% | 0% | 54 | |
| 100% | 12% | 0% | 51 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Avalon City - C2 (MahaRERA P52100014311) is a residential project by Classic Promoters and Builders Private Limited in Dapodi, Pune 411012. It was launched in November 2017. It has 88 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in September 2024, after an extension of 3 years from the original September 2021. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
81 of its 88 units are booked (92%). Since the December 2025 update, 2 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.