Newton Homes Hadapsar Phase III

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Ravima Venture. Hadapsar, Pune 411028. View on Google Maps

Launched
6 years 11 months originally promised
Possession date (MahaRERA)
1 year 3 months ago. No further extension recordedExtended by 3 months (originally April 2025). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
20 of 6829% booked
Price per sq ft (incl. balconies and terrace)
₹9,4002025 · 10 salesdown 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK2
2 BHK14
3 BHK36
Other units (shops, offices or not given by type)16
Total units68
Buildings1
Land1.2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 25 → 20 · final finishes 40% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
950 – 1,010 sq ft₹86 – 93 lakh

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹9,600 per sq ft13 sales
2025down 2% on 2024₹9,400 per sq ft10 sales

Rate vs other Hadapsar projects, 2025: about 10% lower

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 6 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 50%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%20
100%100%40%25
100%100%0%25
100%100%0%18
100%50%0%9

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Newton Homes Hadapsar Phase III (MahaRERA P52100016523) is a residential project by Ravima Venture in Hadapsar, Pune 411028. It was launched in May 2018. It has 68 units in 1 building: 52 homes (1, 2 & 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2025, after an extension of 3 months from the original April 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

20 of its 68 units are booked (29%). 80% of the 2025 sales we found here were at ₹9,400 per sq ft or less (down 2% on 2024), counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate about 10% lower than at other Hadapsar projects in 2025. Most buyers paid ₹86–93 lakh for flats of 950–1,010 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100016523.Check it on MahaRERA (P52100016523)All projects in Hadapsar, Handewadi