Love Spring, Chikhali

Finishing stageLapsed

Final finishes 95% · completion not yet filed on MahaRERA

by Apex Associates. Chikhali, Pune 411062. View on Google Maps

Launched
4 years 8 months originally promised
Possession date (MahaRERA)
10 months ago. No further extension recordedExtended by 2 years (originally December 2023). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
65 of 11557% booked

Project facts

1 BHK60
2 BHK31
3 BHK24
Total units115
Buildings1
Land0.9 acres
Landowner share37
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 59 → 65 · structure 92% → 100% · final finishes 0% → 95%

Share on WhatsApp

Compared with 4 similar projects in PIN 411062

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411062
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 8 mths3 yrs 3 mths
Possession date extendedBy 2 years4 of 4
Possession date passedYes, due December 20251 ready to move; 2 also past their date
Concrete structure (RCC) complete100%75%
Share of units booked57%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 8 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%65
100%92%0%59
0%0%0%30

"—" means MahaRERA shows no figure for that update.

About this project

Love Spring (MahaRERA P52100020368) is a residential project by Apex Associates in Chikhali, Pune 411062. It was launched in April 2019. It has 115 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

65 of its 115 units are booked (57%). Since the December 2025 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 92% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100020368.Check it on MahaRERA (P52100020368)All projects in Chikhali, Talwade