Skip to main content
← Back

Sai Sparsh, Chikhali

by Vaishnavi Developers & Builders. Chikhali, Pune 411062. View on Google Maps

Launched
2 years 10 months originally promised
Possession date (MahaRERA)
1 year 5 months ago. No further extension recordedExtended by 2 years 7 months (originally October 2022). Why possession dates change
Concrete structure (RCC)
90%Mid-construction
Units booked
48 of 7366% booked

Project facts

1 BHK53
2 BHK9
Other units (shops, offices or not given by type)11
Total units73
Buildings1
Land0.4 acres
Landowner share5
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 64 → 48 · structure 85% → 90%

Share on WhatsApp

Compared with 4 similar projects in PIN 411062

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411062
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths3 yrs 9 mths
Possession date extendedBy 2 years 7 months4 of 4
Possession date passedYes, due May 20252 ready to move; 1 also past their date
Concrete structure (RCC) complete90%80%
Share of units booked66%66%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 10 months have passed
Concrete structure (RCC) 90% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 85%Jun 2024: Concrete structure (RCC) 85%Dec 2024: Concrete structure (RCC) 85%Jun 2025: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 90%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%48
100%85%0%64
100%85%0%39

"—" means MahaRERA shows no figure for that update.

About this project

Sai Sparsh (MahaRERA P52100023299) is a residential project by Vaishnavi Developers & Builders in Chikhali, Pune 411062. It was launched in December 2019. It has 73 units in 1 building: 62 homes (1 & 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in May 2025, after an extension of 2 years 7 months from the original October 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

48 of its 73 units are booked (66%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 85% to 90%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100023299.Check it on MahaRERA (P52100023299)All projects in Chikhali, Talwade