Reelicon Fairy Bell, Sus

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Reelicon Red Homes Private Limited. Sus, Pune 411021. View on Google Maps

Launched
4 years 8 months originally promised
Possession date (MahaRERA)
2 months awayExtended by 3 years (originally December 2023). Why possession dates change
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
66 of 16141% booked
Price per sq ft (incl. balconies and terrace)
₹13,200studios · 2026 so far · 28 sales80% of the 2026 studio sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK96
Other units (shops, offices or not given by type)65
Total units161
Buildings2
Land1.4 acres
Landowner share39
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 99% → 100% · final finishes 50% → 100%

Share on WhatsApp

What buyers paid here

Studios (under 450 sq ft)

₹13,200 per sq ft · studios · 2026 so far · 28 sales

80% of the 2026 studio sales we found were at this rate or less

2026 so far₹13,200 per sq ft28 sales

Sizes 170 – 280 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 8 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 50%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 99%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 48%Jun 2024: Final finishes 48%Dec 2024: Final finishes 48%Jun 2025: Final finishes 48%Dec 2025: Final finishes 50%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%66
100%99%50%66
100%50%48%102
100%50%48%101
100%50%48%99

"—" means MahaRERA shows no figure for that update.

About this project

Reelicon Fairy Bell (MahaRERA P52100020477) is a residential project by Reelicon Red Homes Private Limited in Sus, Pune 411021. It was launched in April 2019. It has 161 units in 2 buildings: 96 homes (2 BHK) and 65 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

66 of its 161 units are booked (41%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 99% to 100%. Its studios (under 450 sq ft) sold at ₹13,200 per sq ft or less in 2026 (28 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.