Skip to main content
← Back

Perinsheri Pinnac Greens, Kothrud

Lapsed

by F. S. Mazda & Pinnac Housing Associates LLP. Kothrud, Pune 411038. View on Google Maps

Launched
4 years 1 month originally promised
Possession date (MahaRERA)
1 year 10 months ago. No further extension recordedExtended by 1 year 6 months (originally June 2023). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
41 of 7257% booked
Price per sq ft (incl. balconies and terrace)
₹15,5002026 so far · 21 salesup 8% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK24
3 BHK48
Total units72
Buildings2
Land1.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 25% → 80%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,280 – 1,340 sq ft₹1.66 – 2.07 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹14,400 per sq ft10 sales
2026 so farup 8% on 2025₹15,500 per sq ft21 sales

Rate vs other Kothrud projects, 2026: about 5% lower

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 80%Jun 2024: Concrete structure (RCC) 92%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%41
100%100%25%41
100%100%0%35
100%92%0%33
100%80%0%32

"—" means MahaRERA shows no figure for that update.

About this project

Perinsheri Pinnac Greens (MahaRERA P52100021115) is a residential project by F. S. Mazda & Pinnac Housing Associates LLP in Kothrud, Pune 411038. It was launched in May 2019. It has 72 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year 6 months from the original June 2023. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 80% complete. MahaRERA records do not show it as ready to move in.

41 of its 72 units are booked (57%). 80% of the 2026 (so far) sales we found here were at ₹15,500 per sq ft or less (up 8% on 2025), counting balconies and terrace in the size, based on 21 registered sales. Buyers here paid a rate about 5% lower than at other Kothrud projects in 2026. Most buyers paid ₹1.66–2.07 crore for flats of 1,280–1,340 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100021115.Check it on MahaRERA (P52100021115)All projects in Kothrud