Skip to main content
← Back

Geras World of Joy D, Wagholi

Lapsed

by Gera Developments Private Limited. Wagholi, Pune 412207. View on Google Maps

Launched
6 years promised
Possession date (MahaRERA)
1 year ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
315 of 316100% booked

Project facts

2 BHK190
3 BHK126
Total units316
Buildings3
Land2.3 acres
Complaints on MahaRERA (filed by or against the builder)1
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 6 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 84%Jun 2024: Final finishes 84%Dec 2024: Final finishes 84%Jun 2025: Final finishes 84%Dec 2025: Final finishes 84%Jul 2026: Final finishes 84%Excavation 100%Concrete structure (RCC) 100%Final finishes 84%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%84%315

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Geras World of Joy D (MahaRERA P52100022598) is a residential project by Gera Developments Private Limited in Wagholi, Pune 412207. It was launched in October 2019. It has 316 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2025. That date has passed and no extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 84% complete. MahaRERA records do not show it as ready to move in.

315 of its 316 units are booked (100%).

Gera's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA17
Completed without extending the possession date1
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder2
Typical time from launch to 100% structure4 years 1 month
Complaints on MahaRERA, all Gera projects78 (11 of 17 projects)

See all Gera projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100022598.Check it on MahaRERA (P52100022598)All projects in Wagholi