Ganga Dham Tower C Bibvewadi Pune, Camp
Lapsed
by Legends County Landmark Pvt Ltd. Camp, Pune 411001. View on Google Maps
- Launched
- 6 years 5 months promised
- Possession date (MahaRERA)
- 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 36%Mid-constructionAverage across 4 buildings
- Units booked
- 51 of 12441% booked
Project facts
| 3 BHK | 31 |
|---|---|
| 4 BHK | 62 |
| 5+ BHK | 31 |
| Total units | 124 |
| Buildings | 4 |
| Land | 1.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 18% → 36% · final finishes 1% → 2%
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 25% | 36% | 2% | 51 | |
| 25% | 18% | 1% | 51 | |
| 25% | 14% | 1% | 51 | |
| 25% | 6% | 0% | 47 | |
| 25% | 0% | 0% | 35 |
"—" means MahaRERA shows no figure for that update.
About this project
Ganga Dham Tower C Bibvewadi Pune (MahaRERA P52100023864) is a residential project by Legends County Landmark Pvt Ltd in Camp, Pune 411001. It was launched in January 2020. It has 124 units in 4 buildings, with 3, 4 & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction, averaged across its 4 buildings: excavation 25% complete, structure (RCC) 36% complete, final finishes 2% complete. MahaRERA records do not show it as ready to move in.
51 of its 124 units are booked (41%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 18% to 36%.
Goel Ganga's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 61 |
|---|---|
| Completed without extending the possession date | 18 |
| Completed after an extension, or lapsed | 14 |
| Under construction | 29 |
| Possession date extended by the builder | 16 |
| Typical time from launch to 100% structure | 5 years 1 month |
| Complaints on MahaRERA, all Goel Ganga projects | 141 (27 of 61 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.