Skip to main content
← Back

Ganga Dham Tower C Bibvewadi Pune, Camp

Lapsed

by Legends County Landmark Pvt Ltd. Camp, Pune 411001. View on Google Maps

Launched
6 years 5 months promised
Possession date (MahaRERA)
4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
36%Mid-constructionAverage across 4 buildings
Units booked
51 of 12441% booked

Project facts

3 BHK31
4 BHK62
5+ BHK31
Total units124
Buildings4
Land1.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 18% → 36% · final finishes 1% → 2%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 6 years 5 months have passed
Concrete structure (RCC) 36% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 25%Jun 2024: Excavation 25%Dec 2024: Excavation 25%Jun 2025: Excavation 25%Dec 2025: Excavation 25%Jul 2026: Excavation 25%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 6%Dec 2024: Concrete structure (RCC) 14%Jun 2025: Concrete structure (RCC) 14%Dec 2025: Concrete structure (RCC) 18%Jul 2026: Concrete structure (RCC) 36%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 1%Jun 2025: Final finishes 1%Dec 2025: Final finishes 1%Jul 2026: Final finishes 2%Concrete structure (RCC) 36%Excavation 25%Final finishes 2%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
25%36%2%51
25%18%1%51
25%14%1%51
25%6%0%47
25%0%0%35

"—" means MahaRERA shows no figure for that update.

About this project

Ganga Dham Tower C Bibvewadi Pune (MahaRERA P52100023864) is a residential project by Legends County Landmark Pvt Ltd in Camp, Pune 411001. It was launched in January 2020. It has 124 units in 4 buildings, with 3, 4 & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction, averaged across its 4 buildings: excavation 25% complete, structure (RCC) 36% complete, final finishes 2% complete. MahaRERA records do not show it as ready to move in.

51 of its 124 units are booked (41%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 18% to 36%.

Goel Ganga's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA61
Completed without extending the possession date18
Completed after an extension, or lapsed14
Under construction29
Possession date extended by the builder16
Typical time from launch to 100% structure5 years 1 month
Complaints on MahaRERA, all Goel Ganga projects141 (27 of 61 projects)

See all Goel Ganga projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100023864.Check it on MahaRERA (P52100023864)All projects in Camp, Koregaon Park