Lodha Bella Vita, Mohammadwadi

by Lodha Developers Limited. Mohammadwadi, Pune 411060. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Jul 2026 – Dec 2027varies by phase1 of 5 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
79%Mid-construction3 of 5 phases with structure completeWeighted across 5 phases
Units booked
1,071 of 1,12295% booked

Project facts

2 BHK500
3 BHK329
4 BHK259
5+ BHK34
Total units1,122
Buildings11
Land3.5 acres
Phases5
MahaRERA complaints (filed by or against the builder)4

Since Dec 2025: booked 1,012 → 1,071

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Lodha Pune NIBM Project
Mid-construction
P5210002421547060%98%
Lodha Pune NIBM Project-Tower 6
Completed
P52100034751113100%99%
Lodha Pune NIBM Project-Tower 10
Nearing possession
P52100035060114100%93%
Lodha Pune NIBM Project-Tower 5
Completed
P52100045768111100%98%
Lodha Pune NIBM Project- Tower 7,8 and 9
Mid-construction
P5210004608131485%90%
Show updates by phase

Lodha Pune NIBM Project (P52100024215)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%60%41%460
100%96%42%440
100%93%40%439
100%88%0%441

"—" means MahaRERA shows no figure for that update.

Lodha Pune NIBM Project-Tower 6 (P52100034751)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%112
100%100%40%100
100%76%0%94
100%52%0%92
100%8%0%66

"—" means MahaRERA shows no figure for that update.

Lodha Pune NIBM Project-Tower 10 (P52100035060)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%106
100%100%0%101
100%47%0%99
100%23%0%98
100%0%0%97

"—" means MahaRERA shows no figure for that update.

Lodha Pune NIBM Project-Tower 5 (P52100045768)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%109
100%100%80%107
100%97%0%105
100%83%0%105
100%18%0%89

"—" means MahaRERA shows no figure for that update.

Lodha Pune NIBM Project- Tower 7,8 and 9 (P52100046081)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%284
100%60%0%244
67%0%0%119
0%0%0%35

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Lodha Bella Vita is a project by Lodha Developers Limited in Mohammadwadi, Pune 411060, registered with MahaRERA as 5 phases (P52100024215, P52100034751, P52100035060, P52100045768, P52100046081). The first phase was launched in January 2020. Together the phases have 1,122 units in 11 buildings, with 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 2 are completed.

The phases' registered possession dates run from July 2026 to December 2027; 1 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 79% complete and final finishes 37% complete. 3 of the 5 phases have their structure complete.

1,071 of the 1,122 units reported for sale are booked (95%).

Lodha's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA56
Completed without extending the possession date15
Completed after an extension0
Lapsed0
Under construction41
Possession date extended on the builder's application5
Typical time from launch to 100% structure3 years 7 months
MahaRERA complaints (filed by or against the builder), all Lodha projects36 (17 of 56 projects)

See all Lodha projects →

Source: MahaRERA registrations P52100024215, P52100034751, P52100035060, P52100045768 and P52100046081.Open MahaRERA and search P52100024215All projects in Mohammadwadi, Undri