Trident Business Park, Wakad

Lapsed

by Paranjape Schemes (Construction) Ltd. Wakad, Pune 411057. View on Google Maps

Launched
5 years 1 month originally promised
Possession date (MahaRERA)
4 months ago. No further extension recordedExtended by 9 months (originally September 2025). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
153 of 20874% booked

Project facts

1 BHK146
Other units (shops, offices or not given by type)62
Total units208
Buildings1
Land1.9 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 35%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 70%Jun 2025: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%153
100%70%0%98
100%50%0%98
100%35%0%98

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Trident Business Park (MahaRERA P52100025946) is a residential project by Paranjape Schemes (Construction) Ltd in Wakad, Pune 411057. It was launched in August 2020. It has 208 units in 1 building: 146 homes (1 BHK) and 62 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 9 months from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.

153 of its 208 units are booked (74%).

Paranjape's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA29
Completed without extending the possession date12
Completed after an extension, or lapsed7
Under construction10
Possession date extended by the builder6
Typical time from launch to 100% structure7 years
Complaints on MahaRERA, all Paranjape projects60 (9 of 29 projects)

See all Paranjape projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.