Ambrosia Alley, Hadapsar

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Ambrosia Landmark Private Limited. Hadapsar, Pune 411028. View on Google Maps

Launched
4 years 8 months originally promised
Possession date (MahaRERA)
8 months awayExtended by 2 years (originally June 2025). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
44 of 7459% booked
Price per sq ft (incl. balconies and terrace)
₹9,3002026 so far · 16 salesdown 10% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK11
2 BHK50
3 BHK2
Other units (shops, offices or not given by type)11
Total units74
Buildings1
Land1 acre
Landowner share30
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 43 → 44 · final finishes 95% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
790 – 800 sq ft₹71 – 74 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹9,800 per sq ft13 sales
2025up 5% on 2024₹10,300 per sq ft15 sales
2026 so fardown 10% on 2025₹9,300 per sq ft16 sales

Rate vs other Hadapsar projects, 2026: about 15% lower

Compared with 3 similar projects in PIN 411028

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 8 mths3 yrs 4 mths
Possession date extendedBy 2 years1 of 3
Possession date (MahaRERA)June 2027December 2026
Concrete structure (RCC) complete100%100%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 8 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 95%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%44
100%100%95%43
0%0%0%28

"—" means MahaRERA shows no figure for that update.

About this project

Ambrosia Alley (MahaRERA P52100026792) is a residential project by Ambrosia Landmark Private Limited in Hadapsar, Pune 411028. It was launched in October 2020. It has 74 units in 1 building: 63 homes (1, 2 & 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 2 years from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

44 of its 74 units are booked (59%). Since the December 2025 update, 1 more unit has been booked. 80% of the 2026 (so far) sales we found here were at ₹9,300 per sq ft or less (down 10% on 2025), counting balconies and terrace in the size, based on 16 registered sales. Buyers here paid a rate about 15% lower than at other Hadapsar projects in 2026. Most buyers paid ₹71–74 lakh for flats of 790–800 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100026792.Check it on MahaRERA (P52100026792)All projects in Hadapsar, Handewadi