Nyati Exuberance, Undri

by Nyati Builders Private Limited. Undri, Pune 411060. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Mar 2025 – Mar 2027varies by phase3 of 4 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
92%Mid-construction3 of 4 phases with structure completeWeighted across 4 phases
Units booked
497 of 60283% booked
Price per sq ft
₹8,3002026 salesup 6% on 2025See what buyers paid

Project facts

1 RK64
2 BHK520
Total units602
Buildings9
Land3.6 acres
Phases4
MahaRERA complaints (filed by or against the builder)2

Since Dec 2025: booked 436 → 497

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 700 sq ft₹55 – 59 lakh2026 sales

Price per sq ft, year by year

2023₹6,900 per sq ft
2024up 4% on 2023₹7,200 per sq ft
2025up 8% on 2024₹7,800 per sq ft
2026up 6% on 2025₹8,300 per sq ft

Registered sales across all 4 phases.

Compared with the typical Undri rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Nyati Exuberance I
Nearing possession Lapsed
P52100027031168100%100%
Nyati Exuberance III
Completed
P521000349320100%28%
Nyati Exuberance II
Nearing possession Lapsed
P5210004872040100%100%
Nyati Exuberance IV
Mid-construction
P5210005357631285%85%
Show updates by phase

Nyati Exuberance I (P52100027031)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%168
100%99%63%159
100%83%2%148

"—" means MahaRERA shows no figure for that update.

Nyati Exuberance III (P52100034932)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
45%83%39%23
35%66%0%18
0%30%0%17

"—" means MahaRERA shows no figure for that update.

Nyati Exuberance II (P52100048720)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%40
100%100%64%40
100%95%48%40
100%8%0%39

"—" means MahaRERA shows no figure for that update.

Nyati Exuberance IV (P52100053576)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%58%266
100%76%25%205
100%41%4%103
100%16%0%11
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Nyati Exuberance is a project by Nyati Builders Private Limited in Undri, Pune 411060, registered with MahaRERA as 4 phases (P52100027031, P52100034932, P52100048720, P52100053576). The first phase was launched in November 2020. Together the phases have 602 units in 9 buildings, with 1 RK & 2 BHK homes as registered with MahaRERA. On MahaRERA, 2 are lapsed, 1 is completed and 1 is active.

The phases' registered possession dates run from March 2025 to March 2027; 3 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 92% complete and final finishes 61% complete. 3 of the 4 phases have their structure complete.

497 of the 602 units reported for sale are booked (83%). In 2026 registered sales, 80% of flats here sold at ₹8,300 per sq ft or less (up 6% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Undri rate in 2026. Most buyers paid ₹55–59 lakh for 2 BHK flats of about 700 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Nyati's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA48
Completed without extending the possession date24
Completed after an extension3
Lapsed9
Under construction12
Possession date extended on the builder's application6
Typical time from launch to 100% structure2 years 1 month
MahaRERA complaints (filed by or against the builder), all Nyati projects32 (14 of 48 projects)

See all Nyati projects →

Source: MahaRERA registrations P52100027031, P52100034932, P52100048720 and P52100053576.Open MahaRERA and search P52100027031All projects in Mohammadwadi, Undri