Skip to main content
← Back

Ganga Vasant, Mohammadwadi

by Ganraj Township LLP. Mohammadwadi, Pune 411060. View on Google Maps

Launched
4 years 1 month originally promised
Possession date (MahaRERA)
1 year 8 months awayExtended by 3 years 6 months (originally December 2024). Why possession dates change
Concrete structure (RCC)
63%Mid-constructionAverage across 2 buildings
Units booked
35 of 11231% booked

Project facts

1 BHK56
2 BHK56
Total units112
Buildings2
Land1 acre
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 54% → 63%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 1 month have passed
Concrete structure (RCC) 63% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 50%Dec 2024: Excavation 95%Jun 2025: Excavation 95%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 54%Jul 2026: Concrete structure (RCC) 63%Dec 2023: Final finishes 0%Jun 2024: Final finishes 30%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 63%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%63%50%35
100%54%50%35
95%50%50%9
50%50%30%9
50%0%0%9

"—" means MahaRERA shows no figure for that update.

About this project

Ganga Vasant (MahaRERA P52100027099) is a residential project by Ganraj Township LLP in Mohammadwadi, Pune 411060. It was launched in November 2020. It has 112 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, extended by 3 years 6 months from the original December 2024. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 63% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

35 of its 112 units are booked (31%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 54% to 63%.

Goel Ganga's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA61
Completed without extending the possession date18
Completed after an extension, or lapsed14
Under construction29
Possession date extended by the builder16
Typical time from launch to 100% structure5 years 1 month
Complaints on MahaRERA, all Goel Ganga projects141 (27 of 61 projects)

See all Goel Ganga projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100027099.Check it on MahaRERA (P52100027099)All projects in Mohammadwadi, Undri