Life Republic Sector R10 10th Avenue Universe, Jambhe

Ready to move

by Kolte-Patil Planet Real Estate Private Limited. Jambhe, Pune 411057. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2024 – Dec 2027varies by phase1 of 4 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
100%Ready to move4 of 4 phases with structure completeWeighted across 4 phases
Units booked
1,550 of 1,61096% booked
Price per sq ft
₹9,1002026 salesup 11% on 2025See what buyers paid

Project facts

1 BHK733
2 BHK717
Total units1,610
Buildings7
Land4.7 acres
Phases4
MahaRERA complaints (filed by or against the builder)27

Since Dec 2025: booked 1,546 → 1,550

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 460 sq ft₹35 – 37 lakh2024 sales
2 BHKabout 630 sq ft₹50 – 59 lakh2025 sales
3 BHKabout 1,130 sq ft₹61 – 70 lakh2025 sales

Price per sq ft, year by year

2023₹7,600 per sq ft
2024up 3% on 2023₹7,800 per sq ft
2025up 5% on 2024₹8,200 per sq ft
2026up 11% on 2025₹9,100 per sq ft

Studios (under 450 sq ft): ₹9,100 per sq ft in 2025 sales, up 12% on 2024. Sizes about 440 sq ft.

Registered sales across all 4 phases.

Compared with the typical Jambhe rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Studios are priced separately from flats and are not used in area price comparisons or on the Property rates page.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Life Republic/Sector R10/10th Avenue/Universe Phase-I
Ready to move Lapsed
P52100027629577100%95%
Life Republic/Sector R10/10th Avenue/Universe Phase-II
Ready to move Lapsed
P52100030072398100%96%
Life Republic R10 Universe, Phase IV
Ready to move Lapsed
P52100047317238100%98%
Life Republic/Sector R10/10th Avenue/Universe Phase V
Ready to move
P52100048624237100%98%
Show updates by phase

Life Republic/Sector R10/10th Avenue/Universe Phase-I (P52100027629)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%596
100%100%79%596
100%94%43%596

"—" means MahaRERA shows no figure for that update.

Life Republic/Sector R10/10th Avenue/Universe Phase-II (P52100030072)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%430
100%100%72%409
100%78%38%409

"—" means MahaRERA shows no figure for that update.

Life Republic R10 Universe, Phase IV (P52100047317)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%234
100%100%62%234
100%78%0%208
100%53%0%208
100%22%0%208

"—" means MahaRERA shows no figure for that update.

Life Republic/Sector R10/10th Avenue/Universe Phase V (P52100048624)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%290
100%100%100%286
100%100%0%93
100%75%0%93
100%13%0%93

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Life Republic Sector R10 10th Avenue Universe is a project by Kolte-Patil Planet Real Estate Private Limited in Jambhe, Pune 411057, registered with MahaRERA as 4 phases (P52100027629, P52100030072, P52100047317, P52100048624). The first phase was launched in December 2020. Together the phases have 1,610 units in 7 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are lapsed and 1 is active.

The phases' registered possession dates run from December 2024 to December 2027; 1 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 96% complete. 4 of the 4 phases have their structure complete.

1,550 of the 1,610 units reported for sale are booked (96%). In 2026 registered sales, 80% of flats here sold at ₹9,100 per sq ft or less (up 11% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Jambhe rate in 2026. Most buyers paid ₹35–37 lakh for 1 RK / 1 BHK flats of about 460 sq ft (2024 sales); ₹50–59 lakh for 2 BHK flats of about 630 sq ft (2025 sales); ₹61–70 lakh for 3 BHK flats of about 1,130 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra. Its studios (under 450 sq ft) sold at ₹9,100 per sq ft or less in 2025; studios are priced separately from flats.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension2
Lapsed15
Under construction35
Possession date extended on the builder's application4
Typical time from launch to 100% structure3 years
MahaRERA complaints (filed by or against the builder), all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Source: MahaRERA registrations P52100027629, P52100030072, P52100047317 and P52100048624.Open MahaRERA and search P52100027629All projects in Wakad, Hinjewadi, Marunji