Ravinanda Aamrai Phase II Building B2, Dhayari
by Om Sai Developers. Dhayari, Pune 411041. View on Google Maps
- Launched
- 4 years 10 months originally promised
- Possession date (MahaRERA)
- 2 years 2 months awayExtended by 3 years (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 96 of 21345% booked
Project facts
| 1 BHK | 106 |
|---|---|
| 2 BHK | 107 |
| Total units | 213 |
| Buildings | 2 |
| Land | 1.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 89 → 96 · structure 88% → 100% · final finishes 50% → 25% · possession date December 2025 → December 2028 · total units 126 → 213
Compared with 3 similar projects in PIN 411041
Projects with 100–450 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 10 mths | 4 yrs 2 mths |
| Possession date extended | By 3 years | 2 of 3 |
| Possession date (MahaRERA) | December 2028 | September 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 45% | 78% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 6 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Majestique Swapnangan Wing A and Wing B | October 2021 | September 2026 | 100% | 165 of 210 booked (79%) |
| Aqura Pride | November 2021 | September 2026 | 100% | 103 of 132 booked (78%) |
| Majestique Mrugavarsha Phase III | February 2022 | December 2026 | 0% | 29 of 140 booked (21%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 96 | |
| 100% | 88% | 50% | 89 | |
| 100% | 60% | 0% | 81 | |
| 100% | 60% | 0% | 61 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Ravinanda Aamrai Phase II Building B2 (MahaRERA P52100028220) is a residential project by Om Sai Developers in Dhayari, Pune 411041. It was launched in February 2021. It has 213 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, extended by 3 years from the original December 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.
96 of its 213 units are booked (45%). Since the December 2025 update, 7 more units have been booked, the reported concrete structure (RCC) has gone from 88% to 100% and the possession date has moved from December 2025 to December 2028.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.