- Launched
- 4 years 6 months promised
- Possession date (MahaRERA)
- 1 year 1 month ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 49 of 7962% booked
Project facts
| 1 RK | 1 |
|---|---|
| 1 BHK | 1 |
| 2 BHK | 28 |
| 3 BHK | 48 |
| 4 BHK | 1 |
| Total units | 79 |
| Buildings | 1 |
| Land | 0.4 acres |
| Rehab units | 30 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 50 → 49 · total units 62 → 79
Compared with 4 similar projects in PIN 411038
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 6 mths | 3 yrs 7 mths |
| Possession date extended | No | 3 of 4 |
| Possession date passed | Yes, due September 2025 | 1 ready to move; 2 also past their date |
| Concrete structure (RCC) complete | 100% | 95% |
| Share of units booked | 62% | 36% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Keshar | April 2021 | March 2025 | 90% | 50 of 105 booked (48%) |
| Indira Shankar Nagari Pushkar 1 & Pushkar 2 | May 2021 | February 2027 | 15% | 37 of 149 booked (25%) |
| Dwarka | July 2021 | December 2025 | 100% | 6 of 40 booked (15%) |
| Elitas | August 2021 | July 2026 | 100% | 111 of 118 booked (94%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 49 | |
| 100% | 100% | 75% | 50 | |
| 100% | 100% | 75% | 65 | |
| 100% | 80% | 0% | 47 |
"—" means MahaRERA shows no figure for that update.
About this project
Janhavi (MahaRERA P52100028769) is a residential project by Amol Ajit Ravetkar in Kothrud, Pune 411038. It was launched in March 2021. It has 79 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete. MahaRERA records do not show it as ready to move in.
49 of its 79 units are booked (62%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.