Elitas, Kothrud
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Eka Buildcon Private Limited. Kothrud, Pune 411038. View on Google Maps
- Launched
- 4 years 11 months promised
- Possession date (MahaRERA)
- 3 months agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 111 of 11894% booked
- Price per sq ft (incl. balconies and terrace)
- ₹13,8002025 · 10 sales80% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 64 |
|---|---|
| 3 BHK | 42 |
| 4 BHK | 12 |
| Total units | 118 |
| Buildings | 1 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹13,800 per sq ft | 10 sales |
|---|
Rate vs other Kothrud projects, 2025: about 20% lower
Compared with 5 similar projects in PIN 411038
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 11 mths | 3 yrs 9 mths |
| Possession date extended | No | 4 of 5 |
| Possession date (MahaRERA) | July 2026 | November 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 94% | 48% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arunali | August 2021 | September 2026 | 100% | 21 of 52 booked (40%) |
| Dodke Palazzo | October 2021 | June 2025 | 100% | 104 of 134 booked (78%) |
| Indira Shankar Nagari Pushkar 1 & Pushkar 2 | May 2021 | February 2027 | 15% | 37 of 149 booked (25%) |
| Keshar | April 2021 | March 2025 | 90% | 50 of 105 booked (48%) |
| Janhavi | March 2021 | September 2025 | 100% | 49 of 79 booked (62%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 111 | |
| 100% | 100% | 30% | 66 | |
| 100% | 100% | 30% | 26 | |
| 100% | 60% | 0% | 26 |
"—" means MahaRERA shows no figure for that update.
About this project
Elitas (MahaRERA P52100030185) is a residential project by Eka Buildcon Private Limited in Kothrud, Pune 411038. It was launched in August 2021. It has 118 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
111 of its 118 units are booked (94%). 80% of the 2025 sales we found here were at ₹13,800 per sq ft or less, counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate about 20% lower than at other Kothrud projects in 2025.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.