The Balmoral Riverside, Baner

by Keywest Realty Pvt Ltd. Baner, Pune 411045. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2027No phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
218 of 27679% booked
Price per sq ft
₹17,2002024 salesup 6% on 2023See what buyers paid

Project facts

2 BHK7
3 BHK133
4 BHK132
5+ BHK4
Total units276
Buildings2
Land0.2 acres
Phases2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,100 – 1,380 sq ft₹1.67 – 2.10 crore2024 sales
4 BHKabout 1,400 – 1,870 sq ft₹2.20 – 3.08 crore2024 sales

Price per sq ft, year by year

2023₹16,300 per sq ft
2024up 6% on 2023₹17,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Balewadi rate in 2024: about 15% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Balmoral Riverside-Tower D, Phase II
Nearing possession
P52100028803138100%91%
The Balmoral Riverside - Tower C, Phase I
Nearing possession
P52100028816138100%67%
Show updates by phase

The Balmoral Riverside-Tower D, Phase II (P52100028803)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%126
100%95%0%126

"—" means MahaRERA shows no figure for that update.

The Balmoral Riverside - Tower C, Phase I (P52100028816)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%92
100%95%0%92

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 411045

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 3 mths4 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jun 2027December 2025
Concrete structure (RCC)100%100%
Units booked79%95%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

The Balmoral Riverside is a project by Keywest Realty Pvt Ltd in Baner, Pune 411045, registered with MahaRERA as 2 phases (P52100028803, P52100028816). The first phase was launched in March 2021. Together the phases have 276 units in 2 buildings, with 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 48% complete. 2 of the 2 phases have their structure complete.

218 of the 276 units reported for sale are booked (79%). In 2024 registered sales, 80% of flats here sold at ₹17,200 per sq ft or less (up 6% on 2023), counting balconies and terrace in the size. Buyers here paid a rate about 15% higher than the typical Balewadi rate in 2024. Most buyers paid ₹1.67–2.10 crore for 3 BHK flats of about 1,100–1,380 sq ft (2024 sales); ₹2.20–3.08 crore for 4 BHK flats of about 1,400–1,870 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100028803 and P52100028816.Open MahaRERA and search P52100028803All projects in Baner, Balewadi, Mahalunge