Skip to main content
← Back

Vaanya Cluster A, Moshi

Lapsed

by Pharande Promoters and Builders. Moshi, Pune 412105. View on Google Maps

Launched
4 years 10 months promised
Possession date (MahaRERA)
7 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
All booked144 units booked

Project facts

2 BHK113
3 BHK31
Total units144
Buildings2
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 4 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 68%Jun 2024: Concrete structure (RCC) 91%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%144
100%100%0%144
100%91%0%142
100%68%0%100

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Vaanya Cluster A (MahaRERA P52100029260) is a residential project by Pharande Promoters and Builders in Moshi, Pune 412105. It was launched in May 2021. It has 144 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026. That date has passed and no extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 30% complete. MahaRERA records do not show it as ready to move in.

All 144 units are booked.

Pharande's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA28
Completed without extending the possession date5
Completed after an extension, or lapsed7
Under construction16
Possession date extended by the builder5
Typical time from launch to 100% structure3 years 1 month
Complaints on MahaRERA, all Pharande projects32 (7 of 28 projects)

See all Pharande projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029260.Check it on MahaRERA (P52100029260)All projects in Charholi, Moshi