Aksha Vrundavan, Chikhali

by Aksha Enterprises. Chikhali, Pune 411062. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2025 – Dec 2027varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
204 of 33162% booked

Project facts

1 BHK163
2 BHK162
Total units331
Buildings3
Land1.2 acres
Phases2

Since Dec 2025: booked 165 → 204

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Aksha Vrundavan II
Ready to move Lapsed
P5210002952595100%99%
Aksha Vrundavan III
Nearing possession
P52100051549230100%47%
Show updates by phase

Aksha Vrundavan II (P52100029525)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%94
100%100%0%54

"—" means MahaRERA shows no figure for that update.

Aksha Vrundavan III (P52100051549)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%110
100%100%0%71
100%43%0%—
50%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 411062

Projects with 150–700 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411062
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs5 yrs 1 mth
Possession date extendedYes0 of 3
Possession date (MahaRERA)Jun 2025 – Dec 2027June 2027
Concrete structure (RCC)100%38%
Units booked62%51%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Aksha Vrundavan is a project by Aksha Enterprises in Chikhali, Pune 411062, registered with MahaRERA as 2 phases (P52100029525, P52100051549). The first phase was launched in June 2021. Together the phases have 331 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2025 to December 2027; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 42% complete. 2 of the 2 phases have their structure complete.

204 of the 331 units reported for sale are booked (62%).

Source: MahaRERA registrations P52100029525 and P52100051549.Open MahaRERA and search P52100029525All projects in Chikhali, Talwade