Magnum Iris, Kesnand

by Urban Homes · Kesnand, Pune 412207 · Map

Launched
Jun 20213 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Nearing possession
Booked
85 of 12071%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
2 BHK
108
3 BHK
11
Total units
120
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Oct 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Jun 2025: Final finishes 15%Dec 2025: Final finishes 15%Jul 2026: Final finishes 15%Oct 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%85
100%100%15%85
100%100%15%85
100%100%15%85

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹28.5 crore spent · latest estimate ₹32.7 crore · Aug 2026

Latest estimate ₹32.7 croreApr 2024: ₹11.2 crore11.2Apr 2024Dec 2024: ₹26.1 crore26.1Dec 2024Jun 2025: ₹28.5 crore28.5Jun 2025Aug 2026: ₹28.5 crore28.5Aug 2026
₹ crore spent
Spent at each update
UpdateSpent
Aug 2026₹28.5 crore
Jun 2025₹28.5 crore
Dec 2024₹26.1 crore
Apr 2024₹11.2 crore

Compared with 5 similar projects in PIN 412207

Projects with 60–250 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 412207
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths4 yrs
Possession date extendedBy 2 yrs4 of 5
Possession date (MahaRERA)Dec 2026Oct 2027
Concrete structure (RCC)100%100%
Units booked71%86%
MahaRERA complaints (filed by or against the builder)00

The 5 projects, latest price per sq ft

Other phases of this project are not included in the similar projects.

About this project

Magnum Iris by Urban Homes is a 120-unit project in Kesnand, Pune 412207, launched in June 2021 with possession due in December 2026. 85 units booked out of total 120 units. The concrete structure (RCC) is complete.

Read full summary

Magnum Iris is a project by Urban Homes in Kesnand, Pune 412207, registered with MahaRERA as P52100029676. It was launched in June 2021. It has 120 units in 2 buildings, with 1 RK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

85 units booked out of total 120 units (71%).