Menlo Homes Kharadi Next Phase 2, Wagholi

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Menlo Realty LLP. Wagholi, Pune 412207. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
55 of 8069% booked
Price per sq ft (incl. balconies and terrace)
₹7,8002024 · 16 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK72
3 BHK8
Total units80
Buildings1
Land0.5 acres
Landowner share25
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 95% → 100% · final finishes 25% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
640 – 670 sq ft₹50 – 52 lakh

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹7,800 per sq ft16 sales

Compared with 6 similar projects in PIN 412207

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths4 yrs 4 mths
Possession date extendedNo4 of 6
Possession date passedYes, due December 20253 ready to move; 0 also past their date
Concrete structure (RCC) complete100%100%
Share of units booked69%74%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 65%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 25%Jun 2024: Final finishes 25%Dec 2024: Final finishes 25%Jun 2025: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%55
100%95%25%55
100%100%25%58
100%65%25%15

"—" means MahaRERA shows no figure for that update.

About this project

Menlo Homes Kharadi Next Phase 2 (MahaRERA P52100032415) is a residential project by Menlo Realty LLP in Wagholi, Pune 412207. It was launched in January 2022. It has 80 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

55 of its 80 units are booked (69%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 95% to 100%. 80% of the 2024 sales we found here were at ₹7,800 per sq ft or less, counting balconies and terrace in the size, based on 16 registered sales. Most buyers paid ₹50–52 lakh for flats of 640–670 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032415.Check it on MahaRERA (P52100032415)All projects in Wagholi