Skip to main content
← Back

Mantra Mirari Phase 1, Mundhwa

Lapsed

by Mantra Residences Mundhwa Private Limited. Mundhwa, Pune 411036. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
1 year 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
134 of 18572% booked

Project facts

3 BHK84
4 BHK84
Other units (shops, offices or not given by type)17
Total units185
Buildings3
Land1.2 acres
Landowner share51
Complaints on MahaRERA (filed by or against the builder)3
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 10%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 15%Dec 2024: Final finishes 60%Jun 2025: Final finishes 60%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Excavation 100%Concrete structure (RCC) 100%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%67%134
100%100%60%134
100%100%15%133
100%10%0%130

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Mantra Mirari Phase 1 (MahaRERA P52100030037) is a residential project by Mantra Residences Mundhwa Private Limited in Mundhwa, Pune 411036. It was launched in July 2021. It has 185 units in 3 buildings: 168 homes (3 & 4 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025. That date has passed and no extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 67% complete. MahaRERA records do not show it as ready to move in.

134 of its 185 units are booked (72%).

Mantra's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA80
Completed without extending the possession date41
Completed after an extension, or lapsed16
Under construction23
Possession date extended by the builder7
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all Mantra projects58 (32 of 80 projects)

See all Mantra projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100030037.Check it on MahaRERA (P52100030037)All projects in Mundhwa, Keshavnagar