Skip to main content
← Back

Prime Serenity, Punawale

by Prime Reality. Punawale, Pune 411033. View on Google Maps

Launched
6 years 4 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
114 of 15673% booked
Price per sq ft (incl. balconies and terrace)
₹7,6002025 · 22 salesup 10% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK83
3 BHK47
Other units (shops, offices or not given by type)26
Total units156
Buildings1
Land0.8 acres
Landowner share16
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
970 – 990 sq ft₹70 – 75 lakh

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹6,900 per sq ft23 sales
2025up 10% on 2024₹7,600 per sq ft22 sales

Rate vs other Punawale projects, 2025: about 5% lower

Compared with 3 similar projects in PIN 411033

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 4 mths4 yrs 3 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)December 2027May 2028
Concrete structure (RCC) complete100%100%
Share of units booked73%71%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
5 years 2 months of the promised 6 years 4 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 60%Jun 2025: Final finishes 60%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%114
100%100%60%123
100%100%0%93
100%100%0%80

"—" means MahaRERA shows no figure for that update.

About this project

Prime Serenity (MahaRERA P52100030479) is a residential project by Prime Reality in Punawale, Pune 411033. It was launched in August 2021. It has 156 units in 1 building: 130 homes (2 & 3 BHK) and 26 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete. MahaRERA records do not show it as ready to move in.

114 of its 156 units are booked (73%). 80% of the 2025 sales we found here were at ₹7,600 per sq ft or less (up 10% on 2024), counting balconies and terrace in the size, based on 22 registered sales. Buyers here paid a rate about 5% lower than at other Punawale projects in 2025. Most buyers paid ₹70–75 lakh for flats of 970–990 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100030479.Check it on MahaRERA (P52100030479)All projects in Tathawade, Punawale, Jambhe