Skip to main content
← Back

Velvet Villas Phase 1, Manjari Khurd

by Ashdan Developers Private Limited. Manjari Khurd, Pune 412307. View on Google Maps

Launched
4 years 1 month originally promised
Possession date (MahaRERA)
2 months awayExtended by 1 year (originally December 2025). Why possession dates change
Concrete structure (RCC)
55%Mid-constructionAverage across 31 buildings
Units booked
19 of 3161% booked

Project facts

Other units (shops, offices or not given by type)31
Total units31
Buildings31
Land2.4 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 15 → 19 · structure 25% → 55% · possession date December 2025 → December 2026 · complaints 0 → 1

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 1 month have passed
Concrete structure (RCC) 55% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 68%Dec 2024: Excavation 68%Jun 2025: Excavation 68%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 55%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 55%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%55%0%19
100%25%0%15
68%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Velvet Villas Phase 1 (MahaRERA P52100031829) is a residential project by Ashdan Developers Private Limited in Manjari Khurd, Pune 412307. It was launched in November 2021. It has 31 units, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction, averaged across its 31 buildings: excavation complete, structure (RCC) 55% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

19 of its 31 units are booked (61%). Since the December 2025 update, 4 more units have been booked, the reported concrete structure (RCC) has gone from 25% to 55% and the possession date has moved from December 2025 to December 2026.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031829.Check it on MahaRERA (P52100031829)All projects in Manjari, Shewalewadi