Waterfront, Hadapsar

Lapsed

by nilesh mohandas navalakha. Hadapsar, Pune 411028. View on Google Maps

Launched
3 years 10 months originally promised
Possession date (MahaRERA)
7 months ago. No further extension recordedExtended by 3 months (originally December 2025). What "Lapsed" means
Concrete structure (RCC)
90%Mid-construction
Units booked
Bookings not reported
Price per sq ft (incl. balconies and terrace)
₹13,700studios · 2025 · 18 sales80% of the 2025 studio sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK7
Total units7
Buildings1
Land0.4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: possession date December 2025 → March 2026 · total units 55 → 7

Share on WhatsApp

What buyers paid here

Studios (under 450 sq ft)

₹13,700 per sq ft · studios · 2025 · 18 sales

80% of the 2025 studio sales we found were at this rate or less

2025₹13,700 per sq ft18 sales

Sizes 240 – 360 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 10 months have passed
Concrete structure (RCC) 90% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 8%Jun 2024: Concrete structure (RCC) 60%Dec 2024: Concrete structure (RCC) 90%Jun 2025: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 90%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%50%—
100%60%0%—
0%8%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Waterfront (MahaRERA P52100033110) is a residential project by nilesh mohandas navalakha in Hadapsar, Pune 411028. It was launched in February 2022. It has 7 units in 1 building, with 1 RK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026, after an extension of 3 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the possession date has moved from December 2025 to March 2026. Its studios (under 450 sq ft) sold at ₹13,700 per sq ft or less in 2025 (18 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033110.Check it on MahaRERA (P52100033110)All projects in Hadapsar, Handewadi