Skip to main content
← Back

Nandan ACE, Balewadi

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Jhamtani Realty Private Limited. Balewadi, Pune 411045. View on Google Maps

Launched
4 years 1 month promised
Possession date (MahaRERA)
7 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
135 of 13898% booked

Project facts

2 BHK4
3 BHK134
Total units138
Buildings1
Land0.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 129 → 135 · final finishes 28% → 100%

Share on WhatsApp

Compared with 6 similar projects in PIN 411045

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 1 mth4 yrs 10 mths
Possession date extendedNo2 of 6
Possession date passedYes, due March 20264 ready to move; 0 also past their date
Concrete structure (RCC) complete100%100%
Share of units booked98%82%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 4 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 95%Jun 2024: Excavation 98%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 40%Dec 2024: Concrete structure (RCC) 86%Jun 2025: Concrete structure (RCC) 86%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 28%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%135
100%100%28%129
100%86%0%105
98%40%0%95
95%0%0%3

"—" means MahaRERA shows no figure for that update.

About this project

Nandan ACE (MahaRERA P52100033562) is a residential project by Jhamtani Realty Private Limited in Balewadi, Pune 411045. It was launched in February 2022. It has 138 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

135 of its 138 units are booked (98%). Since the December 2025 update, 6 more units have been booked.

Jhamtani's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA28
Completed without extending the possession date13
Completed after an extension, or lapsed6
Under construction9
Possession date extended by the builder3
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Jhamtani projects14 (3 of 28 projects)

See all Jhamtani projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033562.Check it on MahaRERA (P52100033562)All projects in Baner, Balewadi, Mahalunge