The Midas Residences Phase 1, Balewadi

by Selenite Properties Private Limited. Balewadi, Pune 411045. View on Google Maps

Launched
4 years 6 months originally promised
Possession date (MahaRERA)
1 year 8 months awayExtended by 1 year 6 months (originally December 2026). Why possession dates change
Concrete structure (RCC)
0%Early stageAverage across 4 buildings
Units booked
119 of 20857% booked
Price per sq ft (incl. balconies and terrace)
₹16,1002026 so far · 68 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK6
2 BHK100
3 BHK102
Total units208
Buildings4
Land5.1 acres
Landowner share28
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 49 → 119

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
760 – 780 sq ft₹1.04 – 1.13 crore
990 – 1,010 sq ft₹1.44 – 1.57 crore
1,120 sq ft₹1.80 – 1.87 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹16,100 per sq ft75 sales
2026 so farabout the same as 2025₹16,100 per sq ft68 sales

Rate vs other Balewadi projects, 2026: about 15% higher

Compared with 6 similar projects in PIN 411045

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 6 mths5 yrs 1 mth
Possession date extendedBy 1 year 6 months0 of 6
Possession date (MahaRERA)June 2028December 2027
Concrete structure (RCC) complete0%90%
Share of units booked57%86%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 4 months of the originally promised 4 years 6 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 5%Jul 2026: Excavation 90%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%119
5%0%0%49
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

The Midas Residences Phase 1 (MahaRERA P52100045688) is a residential project by Selenite Properties Private Limited in Balewadi, Pune 411045. It was launched in June 2022. It has 208 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, extended by 1 year 6 months from the original December 2026. Construction, averaged across its 4 buildings: excavation 90% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

119 of its 208 units are booked (57%). Since the December 2025 update, 70 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹16,100 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 68 registered sales. Buyers here paid a rate about 15% higher than at other Balewadi projects in 2026. Most buyers paid ₹1.04–1.13 crore for flats of 760–780 sq ft, ₹1.44–1.57 crore for 990–1,010 sq ft and ₹1.80–1.87 crore for 1,120 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.