Skip to main content
← Back

BLOOM RESIDENCY - A, B and Commercial Wing, Charholi Khurd

by Bloom Infrastructure. Charholi Khurd, Pune 412105. View on Google Maps

Launched
2 years 8 months originally promised
Possession date (MahaRERA)
10 months ago. No further extension recordedExtended by 1 year (originally December 2024). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
79 of 21836% booked

Project facts

1 BHK112
2 BHK56
Other units (shops, offices or not given by type)50
Total units218
Buildings3
Land2.2 acres
Landowner share80
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 70% → 75%

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 8 mths3 yrs 10 mths
Possession date extendedBy 1 year3 of 6
Possession date passedYes, due December 20253 ready to move; 0 also past their date
Concrete structure (RCC) complete100%100%
Share of units booked36%76%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 8 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 83%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 33%Jun 2024: Final finishes 33%Dec 2024: Final finishes 62%Jun 2025: Final finishes 62%Dec 2025: Final finishes 70%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%79
100%100%70%79
100%100%62%49
100%100%33%52
100%83%33%34

"—" means MahaRERA shows no figure for that update.

About this project

BLOOM RESIDENCY - A, B and Commercial Wing (MahaRERA P52100034545) is a residential project by Bloom Infrastructure in Charholi Khurd, Pune 412105. It was launched in April 2022. It has 218 units in 3 buildings: 168 homes (1 & 2 BHK) and 50 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 75% complete. MahaRERA records do not show it as ready to move in.

79 of its 218 units are booked (36%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100034545.Check it on MahaRERA (P52100034545)All projects in Charholi, Moshi