Shriram Corner Phase 2, Dhayari

Finishing stage

Final finishes 90% · completion not yet filed on MahaRERA

by Vision Properties. Dhayari, Pune 411041. View on Google Maps

Launched
3 years 10 months originally promised
Possession date (MahaRERA)
2 months awayExtended by 8 months (originally April 2026). Why possession dates change
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
90 of 17851% booked

Project facts

1 BHK50
2 BHK84
Other units (shops, offices or not given by type)44
Total units178
Buildings2
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 75 → 90 · final finishes 60% → 90% · possession date April 2026 → December 2026

Share on WhatsApp

Compared with 3 similar projects in PIN 411041

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411041
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths4 yrs 2 mths
Possession date extendedBy 8 months2 of 3
Possession date (MahaRERA)December 2026September 2026
Concrete structure (RCC) complete100%100%
Share of units booked51%78%
Complaints on MahaRERA (filed by or against the builder)06

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 73%Jun 2024: Concrete structure (RCC) 75%Dec 2024: Concrete structure (RCC) 90%Jun 2025: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 10%Jun 2024: Final finishes 25%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 60%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%90
100%100%60%75
100%90%50%112
100%75%25%59
100%73%10%44

"—" means MahaRERA shows no figure for that update.

About this project

Shriram Corner Phase 2 (MahaRERA P52100046296) is a residential project by Vision Properties in Dhayari, Pune 411041. It was launched in June 2022. It has 178 units in 2 buildings: 134 homes (1 & 2 BHK) and 44 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 8 months from the original April 2026. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

90 of its 178 units are booked (51%). Since the December 2025 update, 15 more units have been booked and the possession date has moved from April 2026 to December 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.