Rohan Viti, Wakad

by Rohan Builders & Developers Private Limited. Wakad, Pune 411057. View on Google Maps

Launched
3 years 3 months originally promised
Possession date (MahaRERA)
1 year 2 months awayExtended by 2 years (originally December 2025). Why possession dates change
Concrete structure (RCC)
92%Mid-constructionAverage across 3 buildings
Units booked
88 of 9395% booked
Price per sq ft (incl. balconies and terrace)
₹10,6002025 · 51 salesup 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK1
2 BHK66
3 BHK26
Total units93
Buildings3
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 63 → 88 · structure 67% → 92% · final finishes 0% → 27%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
810 – 860 sq ft₹84 – 89 lakh
1,000 – 1,080 sq ft₹1.10 – 1.16 crore

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,400 per sq ft26 sales
2025up 2% on 2024₹10,600 per sq ft51 sales

Rate vs other Wakad projects, 2025: about 15% higher

Compared with 5 similar projects in PIN 411057

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 3 mths4 yrs 1 mth
Possession date extendedBy 2 years2 of 5
Possession date (MahaRERA)December 2027June 2027
Concrete structure (RCC) complete92%100%
Share of units booked95%87%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 3 months have passed
Concrete structure (RCC) 92% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 73%Jun 2024: Excavation 83%Dec 2024: Excavation 83%Jun 2025: Excavation 83%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 3%Dec 2024: Concrete structure (RCC) 53%Jun 2025: Concrete structure (RCC) 53%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 92%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 27%Excavation 100%Concrete structure (RCC) 92%Final finishes 27%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%27%88
100%67%0%63
83%53%0%30
83%3%0%10
73%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Rohan Viti (MahaRERA P52100046719) is a residential project by Rohan Builders & Developers Private Limited in Wakad, Pune 411057. It was launched in September 2022. It has 93 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 92% complete, final finishes 27% complete. MahaRERA records do not show it as ready to move in.

88 of its 93 units are booked (95%). Since the December 2025 update, 25 more units have been booked and the reported concrete structure (RCC) has gone from 67% to 92%. 80% of the 2025 sales we found here were at ₹10,600 per sq ft or less (up 2% on 2024), counting balconies and terrace in the size, based on 51 registered sales. Buyers here paid a rate about 15% higher than at other Wakad projects in 2025. Most buyers paid ₹84–89 lakh for flats of 810–860 sq ft and ₹1.10–1.16 crore for 1,000–1,080 sq ft.

Rohan's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA32
Completed without extending the possession date16
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 8 months
Complaints on MahaRERA, all Rohan projects17 (11 of 32 projects)

See all Rohan projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100046719.Check it on MahaRERA (P52100046719)All projects in Wakad, Hinjewadi, Marunji