Castle Gate, Chikhali
by Ravikumar Ambalal Shah. Chikhali, Pune 411062. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Dec 2027 – Dec 2028varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 88%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 195 of 28369% booked
Facts
Project facts
| 1 BHK | 114 |
|---|---|
| 2 BHK | 139 |
| Total units | 283 |
| Buildings | 2 |
| Land | 0.6 acres |
| Phases | 2 |
Since Dec 2025: booked 167 → 195
Shortlist 2 or more to compare side by side.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Castle Gate A Wing Nearing possession | P52100046766 | 135 | 100% | 78% | |
| Castle Gate B Wing Mid-construction | P52100051321 | 118 | 75% | 57% |
Show updates by phase
Castle Gate A Wing (P52100046766)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 128 | |
| 100% | 75% | 0% | 115 | |
| 100% | 30% | 0% | 93 | |
| 100% | 5% | 0% | 68 | |
| 100% | 0% | 0% | 12 |
"—" means MahaRERA shows no figure for that update.
Castle Gate B Wing (P52100051321)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 67 | |
| 100% | 40% | 0% | 52 | |
| 100% | 10% | 0% | 13 | |
| 100% | 0% | 0% | 10 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 3 similar projects in PIN 411062
Projects with 100–600 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 4 mths | 5 yrs 1 mth |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2027 – Dec 2028 | June 2027 |
| Concrete structure (RCC) | 88% | 64% |
| Units booked | 69% | 46% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sai Aashiyana | June 2022 | December 2026 | 100% | 168 of 180 booked (93%) |
| Ganesh Siddhi Phase 3 | May 2022 | June 2027 | 20% | 27 of 235 booked (11%) |
| Courtyard 15 NXT | April 2023 | Dec 2028 – Dec 2030 | 64% | 166 of 363 booked (46%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Castle Gate is a project by Ravikumar Ambalal Shah in Chikhali, Pune 411062, registered with MahaRERA as 2 phases (P52100046766, P52100051321). The first phase was launched in September 2022. Together the phases have 283 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.
The phases' registered possession dates run from December 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 88% complete and final finishes 11% complete. 1 of the 2 phases have their structure complete.
195 of the 283 units reported for sale are booked (69%).