Courtyard 15 NXT, Chikhali

by Universal Developments. Chikhali, Pune 411062. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2028 – Dec 2030varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
64%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
166 of 36346% booked

Project facts

1 BHK29
2 BHK184
3 BHK84
Total units363
Buildings2
Land2.6 acres
Phases2

Since Dec 2025: booked 122 → 166

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Courtyard 15 NXT Phase 1
Nearing possession
P52100050572166100%68%
Courtyard 15 NXT Phase 2
Mid-construction
PR126000250080813118%24%
Show updates by phase

Courtyard 15 NXT Phase 1 (P52100050572)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%123
100%81%0%103
100%43%0%83
100%20%0%45
100%0%0%7

"—" means MahaRERA shows no figure for that update.

Courtyard 15 NXT Phase 2 (PR1260002500808)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%0%43
100%7%0%19

"—" means MahaRERA shows no figure for that update.

Compared with 4 similar projects in PIN 411062

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411062
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 6 mths5 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2028 – Dec 2030December 2027
Concrete structure (RCC)64%70%
Units booked46%73%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Courtyard 15 NXT is a project by Universal Developments in Chikhali, Pune 411062, registered with MahaRERA as 2 phases (P52100050572, PR1260002500808). The first phase was launched in April 2023. Together the phases have 363 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 64% complete and final finishes 0% complete. 1 of the 2 phases have their structure complete.

166 of the 363 units reported for sale are booked (46%).

Source: MahaRERA registrations P52100050572 and PR1260002500808.Open MahaRERA and search P52100050572All projects in Chikhali, Talwade