V Uptown, Kiwale
Finishing stage
Final finishes 90% · completion not yet filed on MahaRERA
by Tatvam Constructions Private Limited. Kiwale, Pune 412101. View on Google Maps
- Launched
- 2 years 6 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 1 year 3 months (originally March 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 154 of 19479% booked
Project facts
| 1 BHK | 62 |
|---|---|
| 2 BHK | 66 |
| 3 BHK | 66 |
| Total units | 194 |
| Buildings | 2 |
| Land | 4.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 118 → 154 · final finishes 75% → 90%
Compared with 3 similar projects in PIN 412101
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 6 mths | 3 yrs 2 mths |
| Possession date extended | By 1 year 3 months | 2 of 3 |
| Possession date passed | Yes, due June 2026 | 1 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 79% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Astoria Royals B wing | September 2022 | September 2027 | 100% | 186 of 212 booked (88%) |
| Seventy 7 Skyway | September 2022 | December 2026 | 90% | 44 of 143 booked (31%) |
| Solasta A Building | October 2022 | December 2026 | 100% | 107 of 157 booked (68%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 154 | |
| 100% | 100% | 75% | 118 | |
| 100% | 75% | 10% | 65 | |
| 100% | 50% | 0% | 65 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
V Uptown (MahaRERA P52100046930) is a residential project by Tatvam Constructions Private Limited in Kiwale, Pune 412101. It was launched in September 2022. It has 194 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in June 2026, after an extension of 1 year 3 months from the original March 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
154 of its 194 units are booked (79%). Since the December 2025 update, 36 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.