Skip to main content
← Back

Bellacasa Royale Tower N1, Sus

Finishing stage

Final finishes 90% · completion not yet filed on MahaRERA

by Rachana Life Spaces. Sus, Pune 411021. View on Google Maps

Launched
5 years 2 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stage
Units booked
81 of 8496% booked

Project facts

2 BHK46
3 BHK38
Total units84
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 50 → 81 · final finishes 50% → 90%

Share on WhatsApp

Compared with 3 similar projects in PIN 411021

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths2 yrs 10 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)December 2027December 2027
Concrete structure (RCC) complete100%33%
Share of units booked96%27%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years of the promised 5 years 2 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 53%Jun 2024: Concrete structure (RCC) 73%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 10%Jun 2024: Final finishes 35%Dec 2024: Final finishes 45%Jun 2025: Final finishes 45%Dec 2025: Final finishes 50%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%81
100%100%50%50
100%100%45%50
100%73%35%40
100%53%10%30

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Bellacasa Royale Tower N1 (MahaRERA P52100047367) is a residential project by Rachana Life Spaces in Sus, Pune 411021. It was launched in October 2022. It has 84 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

81 of its 84 units are booked (96%). Since the December 2025 update, 31 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047367.Check it on MahaRERA (P52100047367)All projects in Bavdhan, Pashan, Sus