Kiran Swastik, Sus

by Kiran Creators and Developers Private Limited. Sus, Pune 411021. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2026 – Oct 2028varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
30%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
237 of 42256% booked
Price per sq ft
₹8,3002026 salesabout the same as 2025See what buyers paid

Project facts

2 BHK552
3 BHK332
Total units465
Buildings2
Land0.4 acres
Phases2

Since Dec 2025: booked 170 → 180

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 730 – 810 sq ft₹61 – 67 lakh2026 sales
3 BHKabout 940 – 1,000 sq ft₹74 – 88 lakh2026 sales

Price per sq ft, year by year

2025₹8,300 per sq ft
2026about the same as 2025₹8,300 per sq ft

Registered sales across all 2 phases.

Compared with the typical Sus rate in 2026: about 20% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kiran Swastik Building A
Nearing possession Lapsed
P52100047619240100%75%
Kiran Swastik Building B
Mid-construction
PC12610124000166444%25%
Show updates by phase

Kiran Swastik Building A (P52100047619)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%53%180
100%90%0%170
100%50%0%186
100%0%0%132
100%0%0%111

"—" means MahaRERA shows no figure for that update.

Kiran Swastik Building B (PC1261012400016)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%4%0%57
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 411021

Projects with 400–1,800 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 2 mths5 yrs 4 mths
Possession date extendedYes0 of 3
Possession date (MahaRERA)Jun 2026 – Oct 2028June 2028
Concrete structure (RCC)30%47%
Units booked56%67%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Kiran Swastik is a project by Kiran Creators and Developers Private Limited in Sus, Pune 411021, registered with MahaRERA as 2 phases (P52100047619, PC1261012400016). The first phase was launched in November 2022. Together the phases have 465 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2026 to October 2028; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 30% complete and final finishes 14% complete. 1 of the 2 phases have their structure complete.

237 of the 422 units reported for sale are booked (56%). In 2026 registered sales, 80% of flats here sold at ₹8,300 per sq ft or less (about the same as 2025), counting balconies and terrace in the size. Buyers here paid a rate about 20% lower than the typical Sus rate in 2026. Most buyers paid ₹61–67 lakh for 2 BHK flats of about 730–810 sq ft (2026 sales); ₹74–88 lakh for 3 BHK flats of about 940–1,000 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100047619 and PC1261012400016.Open MahaRERA and search P52100047619All projects in Bavdhan, Pashan, Sus