Little Earth, Kiwale, Kiwale
by Kolte-Patil Developers Limited. Kiwale, Pune 412101. View on Google Maps
- Launched
- First of 6 phases
- Possession dates (MahaRERA)
- Jun 2025 – Apr 2031varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 36%Mid-construction2 of 6 phases with structure completeWeighted across 6 phases
- Units booked
- 217 of 45747% booked · 3 phases not reported
- Price per sq ft
- ₹8,5002026 salesSee what buyers paid
Facts
Project facts
| 2 BHK | 484 |
|---|---|
| 3 BHK | 371 |
| 4 BHK | 10 |
| Total units | 865 |
| Buildings | 7 |
| Land | 23.7 acres |
| Phases | 6 |
Since Dec 2025: booked 88 → 136
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 2 BHK | about 680 – 860 sq ft | ₹58 – 72 lakh | 2026 sales |
| 3 BHK | about 950 – 1,080 sq ft | ₹90 lakh – ₹1.14 crore | 2026 sales |
Price per sq ft, year by year
| 2026 | ₹8,500 per sq ft |
|---|
Registered sales across all 6 phases.
Compared with the typical Kiwale rate in 2026: similar
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 6 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Little Earth, Kiwale Building C16 Ready to move Lapsed | P52100047721 | 115 | 100% | 97% | |
| Little Earth, Kiwale- Building B11 Ready to move | P52100047722 | 172 | 100% | 14% | |
| Little Earth, Kiwale - Building C14 Mid-construction | P52100054389 | 84 | 11% | Not reported | |
| Little Earth, Kiwale - Building C13 Mid-construction | P52100054592 | 84 | 13% | Not reported | |
| Little Earth, Kiwale - Building D1 Early stage | P52100078759 | 170 | 0% | 48% | |
| Little Earth, Kiwale - Building B7 Early stage | PR1260002600560 | 240 | 0% | Not reported |
Show updates by phase
Little Earth, Kiwale Building C16 (P52100047721)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 96% | 112 | |
| 100% | 100% | 96% | 64 | |
| 100% | 100% | 17% | 64 | |
| 100% | 78% | 0% | 64 | |
| 100% | 34% | 0% | 64 |
"—" means MahaRERA shows no figure for that update.
Little Earth, Kiwale- Building B11 (P52100047722)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 100% | 93% | 24 | |
| 50% | 100% | 19% | 24 | |
| 50% | 50% | 1% | 24 | |
| 50% | 19% | 0% | 24 |
"—" means MahaRERA shows no figure for that update.
Little Earth, Kiwale - Building C14 (P52100054389)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 11% | 0% | — | |
| 100% | 4% | 0% | — | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Little Earth, Kiwale - Building C13 (P52100054592)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 13% | 0% | — | |
| 100% | 4% | 0% | — | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Little Earth, Kiwale - Building D1 (P52100078759)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 81 | |
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Little Earth, Kiwale - Building B7 (PR1260002600560)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 4 similar projects in PIN 412101
Projects with 400–1,800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 5 mths | 4 yrs 10 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Jun 2025 – Apr 2031 | September 2027 |
| Concrete structure (RCC) | 36% | 28% |
| Units booked | 47% | 74% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Godrej Serene | October 2022 | June 2027 | 0% | 366 of 557 booked (66%) |
| Presidential Towers | September 2022 | June 2028 | 87% | 504 of 655 booked (77%) |
| Sparkle at Godrej Serene | January 2023 | December 2027 | 0% | Bookings not reported |
| The Rising | April 2023 | Jul 2027 – Dec 2028 | 57% | 431 of 586 booked (74%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
Other phases of this project
About this project
Little Earth, Kiwale is a project by Kolte-Patil Developers Limited in Kiwale, Pune 412101, registered with MahaRERA as 6 phases (P52100047721, P52100047722, P52100054389, P52100054592, P52100078759, PR1260002600560). The first phase was launched in November 2022. Together the phases have 865 units in 7 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. On MahaRERA, 5 are active and 1 is lapsed.
The phases' registered possession dates run from June 2025 to April 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 36% complete and final finishes 31% complete. 2 of the 6 phases have their structure complete.
217 of the 457 units reported for sale are booked (47%); 3 phases have not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹8,500 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Kiwale rate in 2026. Most buyers paid ₹58–72 lakh for 2 BHK flats of about 680–860 sq ft (2026 sales); ₹90 lakh–₹1.14 crore for 3 BHK flats of about 950–1,080 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
Kolte Patil's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 63 |
|---|---|
| Completed without extending the possession date | 11 |
| Completed after an extension | 2 |
| Lapsed | 15 |
| Under construction | 35 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 3 years |
| MahaRERA complaints (filed by or against the builder), all Kolte Patil projects | 100 (28 of 63 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.