Palmspring Towers - A4, A5 and B2, Undri
by Kumar Kering Developers LLP. Undri, Pune 411060. View on Google Maps
- Launched
- 4 years promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 78%Mid-constructionAverage across 4 buildings
- Units booked
- 198 of 21791% booked
Project facts
| 1 BHK | 2 |
|---|---|
| 2 BHK | 163 |
| 3 BHK | 52 |
| Total units | 217 |
| Buildings | 4 |
| Land | 19.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 199 → 198 · structure 67% → 78% · final finishes 38% → 50%
Compared with 5 similar projects in PIN 411060
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs | 4 yrs 4 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | December 2026 | June 2027 |
| Concrete structure (RCC) complete | 78% | 85% |
| Share of units booked | 91% | 67% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| ELINA LIVA Tower I and J | February 2023 | June 2027 | 100% | 178 of 181 booked (98%) |
| Mayuri Adhinathpuram | February 2023 | December 2028 | 100% | 228 of 341 booked (67%) |
| Sukhwani Verde | April 2023 | December 2026 | 62% | 109 of 238 booked (46%) |
| Newquay | May 2023 | June 2027 | 75% | 14 of 128 booked (11%) |
| Lodha Pune NIBM Project- Tower 7,8 and 9 | June 2022 | December 2027 | 85% | 284 of 314 booked (90%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 50% | 198 | |
| 100% | 67% | 38% | 199 | |
| 100% | 58% | 50% | 192 | |
| 100% | 52% | 13% | 180 | |
| 100% | 52% | 3% | 150 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Palmspring Towers - A4, A5 and B2 (MahaRERA P52100048329) is a residential project by Kumar Kering Developers LLP in Undri, Pune 411060. It was launched in December 2022. It has 217 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 78% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
198 of its 217 units are booked (91%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 67% to 78%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.