Mayuri Adhinathpuram, Undri
by Mayuri Landmarksllp. Undri, Pune 411060. View on Google Maps
- Launched
- 4 years 10 months originally promised
- Possession date (MahaRERA)
- 2 years 2 months awayExtended by 1 year (originally December 2027). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 4 buildings
- Units booked
- 228 of 34167% booked
Project facts
| 1 BHK | 136 |
|---|---|
| 2 BHK | 205 |
| Total units | 341 |
| Buildings | 4 |
| Land | 1.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 143 → 228 · structure 75% → 100% · possession date December 2027 → December 2028
Compared with 4 similar projects in PIN 411060
Projects with 150–700 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 10 mths | 4 yrs |
| Possession date extended | By 1 year | 0 of 4 |
| Possession date (MahaRERA) | December 2028 | March 2027 |
| Concrete structure (RCC) complete | 100% | 70% |
| Share of units booked | 67% | 78% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| ELINA LIVA Tower I and J | February 2023 | June 2027 | 100% | 178 of 181 booked (98%) |
| Sukhwani Verde | April 2023 | December 2026 | 62% | 109 of 238 booked (46%) |
| Palmspring Towers - A4, A5 and B2 | December 2022 | December 2026 | 78% | 198 of 217 booked (91%) |
| Nyati Esteban II | October 2023 | September 2027 | 49% | 318 of 500 booked (64%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 35% | 228 | |
| 100% | 75% | 35% | 143 | |
| 50% | 10% | 0% | 46 | |
| 40% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Mayuri Adhinathpuram (MahaRERA P52100049330) is a residential project by Mayuri Landmarksllp in Undri, Pune 411060. It was launched in February 2023. It has 341 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, extended by 1 year from the original December 2027. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes 35% complete. MahaRERA records do not show it as ready to move in.
228 of its 341 units are booked (67%). Since the December 2025 update, 85 more units have been booked, the reported concrete structure (RCC) has gone from 75% to 100% and the possession date has moved from December 2027 to December 2028.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.