The Urbana, Chakan
Lapsed
by Intercontinental Infrastructure Limited. Chakan, Pune 410501. View on Google Maps
- Launched
- 3 years 3 months promised
- Possession date (MahaRERA)
- 7 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 75 of 7995% booked
Project facts
| 1 BHK | 12 |
|---|---|
| 2 BHK | 40 |
| 3 BHK | 27 |
| Total units | 79 |
| Buildings | 1 |
| Land | 3.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 37 → 75 · total units 87 → 79
Compared with 4 similar projects in PIN 410501
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 3 mths | 4 yrs 2 mths |
| Possession date extended | No | 0 of 4 |
| Possession date passed | Yes, due March 2026 | 1 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 74% |
| Share of units booked | 95% | 53% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mungase Towers | March 2023 | December 2026 | 100% | 76 of 144 booked (53%) |
| Pradnyesh Shriniwas | April 2023 | December 2027 | 48% | 54 of 88 booked (61%) |
| Saidatta Paradise Wing C | May 2023 | December 2028 | 100% | 24 of 56 booked (43%) |
| Shree Samarth Shrushti | June 2023 | September 2026 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 75 | |
| 100% | 100% | 30% | 37 | |
| 100% | 100% | 25% | 35 | |
| 100% | 100% | 20% | 42 | |
| 100% | 25% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
The Urbana (MahaRERA P52100048342) is a residential project by Intercontinental Infrastructure Limited in Chakan, Pune 410501. It was launched in December 2022. It has 79 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete. MahaRERA records do not show it as ready to move in.
75 of its 79 units are booked (95%). Since the December 2025 update, 38 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.